Construction Progress

Stage III
Design documentation 100%, excavation 90%, foundations 30%, removal of infrastructure conflicts 100%, drilling and installation of the lower heat source.
In progress
See photos
Stage IV
Excavation 100%, foundations 100%, construction to zero level 95%.
Ahead
till 31 January 2026
Stage V
Aboveground structure (open shell) 100%, installations 10%.
Ahead
till 30 November 2026
Stage VI
Masonry works 50%, internal plasters 10%, installations 20%.
Ahead
till 30 April 2027
Stage VII
Masonry works 90%, internal plasters 75%, screeds 50%, window joinery and external joinery 50%, installations 40%.
Ahead
till 30 November 2027
Stage VIII
Masonry works 95%, internal plasters 95%, screeds 95%, window joinery 90%, facade 30%, internal finishing works 30%, installations 75%.
Ahead
till 28 February 2028
Stage IX
Window joinery 95%, facade 90%, internal finishing works 90%, installations 90%.
Ahead
till 30 June 2028
Stage X
Elevation 100%, internal finishing works 100%, installations 100%, obtaining an occupancy permit.
Ahead
till 30 September 2028